client:
Chevron Nigeria Ltd (CNL)
Project:
Agbami FPSO Mooring Chain Replacement
partners:
RMC & INTERMOOR
Type of Vessel:
Deep Water installation Vessel (DWIV)
Status:
Ongoing
GMT SoW:
Disconnect, retrieve and inspect the top chains, wire ropes, and bottom chains of mooring lines S1, S2, and S3 of the Agbami FPSO and reinstate with new mooring components.
Mooring equipment includes the top chains, all shackle connectors, spiral strand wires, tri-plates, short chain sections, bottom chains, and ROV H-links.
The bottom chain is to be disconnected from the pile chain via the existing ROV H-link.
The existing pile chains and piles are to be reused and all design and engineering necessary to disconnect, inspect, replace and reconnect the specified mooring lines one by one will be done.